Build Schedule
Week 49
We are currently awaiting the removal of a gas pipe on the infant school site. Once this has taken place we will commence with the build schedule. Work on the junior school is underway.
The schedule below describes the activities taking place on site week-by-week. Details may change from time-to-time as we need to be flexible on site, but we will endeavour to keep to the schedule to deliver your community excellent new school buildings, with as little disruption to your community as possible.
Junior School Site Activity
Infant School Site Activity
SITE ACTIVITY
THIS WEEK
49
- Clean and tidy the area
- Concrete landscaping
- Demolition
- Full mechanical and electrical testing/running in
- Inspection and snagging
50
- Final clearance of external
- Final internal clean and tidy
- Staff training
51
- PROJECT COMPLETION AND HANDOVER